Monday
Remove existing suite and tiles / blown render & removal of non load-bearing wall
Tuesday
Re-boarding of walls & ceiling and 1st fix electrics
Wednesday
Joinery work – adding a door frame in the intended new position + wall preparation
Thursday
1st fix plumbing
Friday
Plastering ceiling + tank shower area prior to tiling
Saturday
Plastering walls + wall tiling
Monday
Paint walls & ceiling + fit skirting boards + towel radiator
Tuesday
2nd fix plumbing + gloss skirting
Wednesday
(allow gloss to dry)
Thursday
2nd fix electrics + joinery (door hanging)
This bathroom installation started on a Monday and finished the next Thursday.
For ways to reduce this time, please see below tips to reduce bathroom installation times.
Also, please see my article entitled Top 5 Hidden bathroom installation costs to see examples of what additional work (that you may have not planned for) can occur.